The multi-mode resource-constrained project scheduling problem

Author
Organization
Abstract
This chapter reports on a new solution approach for the multi-mode resource-constrained project scheduling problem (MRCPSP, MPSjprecjCmax). This problem type aims at the selection of a single activity mode from a set of available modes in order to construct a precedence and a (renewable and nonrenewable) resource-feasible project schedule with a minimal makespan. The problem type is known to be N P-hard and has been solved using various exact as well as (meta-)heuristic procedures. The new algorithm splits the problem type into a mode assignment and a single mode project scheduling step. The mode assignment step is solved by a satisfiability (SAT) problem solver and returns a feasible mode selection to the project scheduling step. The project scheduling step is solved using an efficient meta-heuristic procedure from literature to solve the resourceconstrained project scheduling problem (RCPSP). However, unlike many traditional meta-heuristic methods in literature to solve the MRCPSP, the new approach executes these two steps in one run, relying on a single priority list. Straightforward adaptations to the pure SAT solver by using pseudo boolean nonrenewable resource constraints has led to a high quality solution approach in a reasonable computational time. Computational results show that the procedure can report similar or sometimes even better solutions than found by other procedures in literature, although it often requires a higher CPU time.
Keywords
Resource constraints, Makespan minimization, Project scheduling, SAT, Multi-mode

Downloads

  • (...).pdf
    • full text
    • |
    • UGent only
    • |
    • PDF
    • |
    • 404.92 KB

Citation

Please use this url to cite or link to this publication:

MLA
Coelho, José, and Mario Vanhoucke. “The Multi-Mode Resource-Constrained Project Scheduling Problem.” Handbook on Project Management and Scheduling, edited by C Schwindt and J Zimmermann, vol. 1, Springer International Publishing Switzerland, 2015, pp. 491–511, doi:10.1007/978-3-319-05443-8_22.
APA
Coelho, J., & Vanhoucke, M. (2015). The multi-mode resource-constrained project scheduling problem. In C. Schwindt & J. Zimmermann (Eds.), Handbook on project management and scheduling (Vol. 1, pp. 491–511). https://doi.org/10.1007/978-3-319-05443-8_22
Chicago author-date
Coelho, José, and Mario Vanhoucke. 2015. “The Multi-Mode Resource-Constrained Project Scheduling Problem.” In Handbook on Project Management and Scheduling, edited by C Schwindt and J Zimmermann, 1:491–511. Springer International Publishing Switzerland. https://doi.org/10.1007/978-3-319-05443-8_22.
Chicago author-date (all authors)
Coelho, José, and Mario Vanhoucke. 2015. “The Multi-Mode Resource-Constrained Project Scheduling Problem.” In Handbook on Project Management and Scheduling, ed by. C Schwindt and J Zimmermann, 1:491–511. Springer International Publishing Switzerland. doi:10.1007/978-3-319-05443-8_22.
Vancouver
1.
Coelho J, Vanhoucke M. The multi-mode resource-constrained project scheduling problem. In: Schwindt C, Zimmermann J, editors. Handbook on project management and scheduling. Springer International Publishing Switzerland; 2015. p. 491–511.
IEEE
[1]
J. Coelho and M. Vanhoucke, “The multi-mode resource-constrained project scheduling problem,” in Handbook on project management and scheduling, vol. 1, C. Schwindt and J. Zimmermann, Eds. Springer International Publishing Switzerland, 2015, pp. 491–511.
@incollection{7094405,
  abstract     = {{This chapter reports on a new solution approach for the multi-mode resource-constrained project scheduling problem (MRCPSP, MPSjprecjCmax). This problem type aims at the selection of a single activity mode from a set of available modes in order to construct a precedence and a (renewable and nonrenewable) resource-feasible project schedule with a minimal makespan. The problem type is known to be N P-hard and has been solved using various exact as well as (meta-)heuristic procedures. The new algorithm splits the problem type into a mode assignment and a single mode project scheduling step. The mode assignment step is solved by a satisfiability (SAT) problem solver and returns a feasible mode selection to the project scheduling step. The project scheduling step is solved using an efficient meta-heuristic procedure from literature to solve the resourceconstrained project scheduling problem (RCPSP). However, unlike many traditional meta-heuristic methods in literature to solve the MRCPSP, the new approach
executes these two steps in one run, relying on a single priority list. Straightforward adaptations to the pure SAT solver by using pseudo boolean nonrenewable resource
constraints has led to a high quality solution approach in a reasonable computational time. Computational results show that the procedure can report similar or sometimes
even better solutions than found by other procedures in literature, although it often requires a higher CPU time.}},
  author       = {{Coelho, José and Vanhoucke, Mario}},
  booktitle    = {{Handbook on project management and scheduling}},
  editor       = {{Schwindt, C and Zimmermann, J}},
  isbn         = {{978-3-319-05442-1}},
  keywords     = {{Resource constraints,Makespan minimization,Project scheduling,SAT,Multi-mode}},
  language     = {{eng}},
  pages        = {{491--511}},
  publisher    = {{Springer International Publishing Switzerland}},
  series       = {{International Handbooks on Information Systems}},
  title        = {{The multi-mode resource-constrained project scheduling problem}},
  url          = {{http://doi.org/10.1007/978-3-319-05443-8_22}},
  volume       = {{1}},
  year         = {{2015}},
}