Project: Execution and reporting of strain measurements on bridges KW03, KW04 and KW05 in accordance with specification 6_380

project duration
18-MAY-04 – 31-DEC-05
abstract
Execution and reporting of strain measurements on - KW03: Steel tied arch bridge with concrete deck - KW04: Steel arch bridge with concrete deck - KW05: Steel tied arch bridge with ortotropic steel deck, in order to check design and construction.